China has implemented both quantitative and policy incentives for renewable energy development since 2019 and is currently in the policy transition stage. The implementation of renewable portfolio standards (RPSs) is difficult due to the interests of multiple stakeholders, including power generation enterprises, power grid companies, power users, local governments, and the central government. Based on China’s RPS policy and power system reform documents, this research sorted out the core game decision problems of China’s renewable energy industry and established a conceptual game decision model of the renewable energy industry from the perspective of local governments, power generation enterprises and power grid companies. The results reveal that for local governments, the probability of meeting the earnings quota or punishments for not reaching quota completion are the major determinants for active participation in quota supervision. For power grid firms, the willingness to accept renewable electricity quotas depends on the additional cost of receiving renewable electricity and governmental incentives. It is reasonable, from the theoretical perspective, to implement the RPS policy on the power generation side. Electricity reform will help clarify the electricity price system and increase the transparency of the quota implementation process. Policy implications are suggested to achieve sustainable development of the renewable energy industry from price incentives and quantity delivery.
It is widely acknowledged that energy security, environmental protection and climate change are global challenges of international concern. Renewable energy development is an efficient measure to address these threats worldwide. First, with the continuous development of the economy and society, electric power will be increasingly in demand in daily life. The newly emerging source of electricity generation is mostly renewable energy. According to data from the International Renewable Energy Development Agency (IRENA), the global installed capacity of renewable energy in 2019 totalled 2.53 billion kilowatts [
However, the imperfect policy framework of China’s power market requires further improvements to be able to support the sustainable development of the renewable energy industry. With the medium-speed growth of China’s economy in the new normal period and intensive environmental management, the Chinese renewable energy industry has transited from scale development to a wide range of incremental replacement and regional stock replacement stages. According to the 13th five-year plan for renewable energy development, China’s commercial renewable energy consumption was 436 million tons of standard coal in 2015, accounting for 10.1% of the total primary energy consumption, and planned to be over 580 million tons of standard coal in 2020 [
Behind prosperous development, China’s renewable energy industry has the following problems. First, the existing power operation mechanism does not meet the needs of the large-scale development of renewable energy. The fossil fuel-based traditional power system cannot fully meet the requirements of grid-connected operations of fluctuating renewable energy sources. There are still technical barriers to the large-scale grid connection of renewable electricity generation, and it is difficult to effectively implement the policy of fully purchasing renewable energy power. Second, the renewable energy industry is still dependent on policy incentives. It is necessary to further reduce the cost of power generation by promoting technological progress and establishing an efficient market competition mechanism. Third, stakeholders in the renewable energy industry have different interest demands, which restrict the sustainable development of the renewable energy industry. Apart from the high increase rate of installed renewable energy capacity, the utilization rate is relatively low because of the unclear responsibilities and obligations among the relevant stakeholders and the absence of a renewable electricity transmission channel grid. Therefore, stakeholder engagement is significant for the success of renewable energy engineering projects.
Renewable energy development requires joint teamwork with the participation of the central government, local government, power generation enterprises, power grid enterprises and electricity consumers. The implementation of renewable portfolio standards (RPS) is an effective approach to achieve quota targets for all provinces and power grid enterprises through mandatory policies.
The national renewable energy development system determines the overall trend of renewable energy, so the attitude of system makers to renewable energy development is very important to the implementation of the RPS. The national system urges the central government to vigorously promote the development of renewable energy. Second, the enthusiasm of power generation enterprises has played a fundamental role in the development of renewable energy because the final power generation responsibility still needs to be implemented by specific power generation enterprises. The collaborative participation of local governments and power grid enterprises will add wings to the implementation of renewable energy policy, which is also the key to the development of renewable energy.
In the future, public support for renewable energy development will have an important impact on RPS policy and even the whole renewable energy industry. Responsibility sharing and a system of rewards and punishments should be mandatory and flexible, and both incentives and punishments should be emphasized. The RPS policy needs to subdivide responsibility sharing. Especially when the central government issues regional quota targets, the local government should be responsible for detailed rules to measure the contributions of each participant within the policy framework. China has already polished numerous incentives for renewable energy development, such as feed-in tariff prices, auction electricity prices, fiscal subsidies, tax preferences and other policies [
(1) The multi-Stakeholders’ behaviours under RPS
Fan et al. based on the newly proposed provincial RPS for 2020, an integrated planning model composed of a multi-regression model and linear planning model was established to optimize the RE power installation plan for each province in 2020, it alleviates the waste of renewable energy and promotes the efficient utilization of renewable energy in China [
(2) Multi-Stakeholders’ behaviours under RPS by using game theory
Many previous studies used game model, Zhao et al. developed an evolution game model of power producers to analyze the symbiotic evolution between RPS and the electric producers’ behaviour strategies, trading TGC could become the common belief of all power producers, with the scientific design of institutional parameters [
Most of the previous studies used game model to study and analyze power generation companies, but few studies analyzed other stakeholders. This paper mainly analyzes the game and decision-making behaviour of various stakeholders under RPS, discusses the collaborative relationship between the quota system and the existing renewable energy incentive policies, and conducts an internal economic analysis of mechanism coordination, and the main research conclusions and implications are summarized.
China’s renewable energy development in the past 15 years has educated us that feed-in tariffs and other policies have promoted the expansion of the renewable energy market. Compared with other energy technologies, the competitiveness of renewable energy technologies is gradually increasing, but there is still a large gap between them [
Based on the above literature review, the analysis of the game decision-making behaviours of various stakeholders in the RPS and the possible mobilization of the whole society to participate in renewable energy development can provide a basis for the success of a national RPS policy. Therefore, this research establishes a game decision model for analysing stakeholders’ behaviours under RPS policy and finds the key factors that influence stakeholders’ decisions. With the actual parameters, the modelling results would be meaningful to formulate the incentives and punishments for finishing renewable energy targets and to discuss the synergies between RPSs and existing renewable energy policies. Additionally, it is necessary to analyse the game behaviour of each participant and understand the demands of each interest group and the key factors affecting their participation in the RPS policy. This paper mainly focuses on the following three issues. With the background of China’s power system reform, how could this research simulate game behaviours under the framework of China’s RPS? Under the quota system, what are the driving factors for the game behaviour of each agent of interest? What are the possible impacts of the ongoing power market reform on the game process?
As a new policy to promote renewable energy development in China, the success of RPS implementation should consider all-in participation from agents of relevant interest. The evolutionary game and decision analyses in this context are policy regime issues from the view of the game body, game payoff and game circumstance.
Power generation enterprises are responsible for the obligations of renewable power generation, but there are also competitive relationships among the power generation enterprises [
Power grids are central for the achievement of renewable quotas due to their significance in the purchase, transmission, dispatching, distribution and sale of electricity. Renewable energy consumption, therefore, depends largely on the support of the power grid [
The government has the primary obligation to plan, manage and supervise the implementation of RPSs. At the local level, local governments are specifically responsible for the supervision and management of renewable energy procurement [
Consumers of electricity accept renewable electricity consumption. However, the general public on the electricity demand side cannot freely choose power services [
The key determinant of the game decision of each interest group under the RPS policy lies in the cost and benefit mechanism in the process of completing the RPSs [
As electricity has the property of public goods, the consumption of renewable energy electricity requires the supervision of local government. The absence of supervision may lead to a lower willingness of power grid enterprises to accept renewable electricity [
A cost-benefit analysis will be a key consideration in government regulation of RPS. The probability of government regulation (or the degree of regulation) is influenced by the cost of regulation (or the penalty in case of noncompliance) and the probability of quota completion. The government’s participation in RPS implementation will expense certain management costs, including expenditures in the process of task design, supervision and assessment [
If indicator
Indicator | Parameters |
---|---|
Probability of not reaching renewable quotas for local government | |
Probability of reaching renewable quotas for local government | 1 − |
Probability of local government’s participation in RPS | |
Probability of local government’s no participation in RPS | 1 − |
Costs for local government to supervise RPS | |
Reputation benefits of local government in RPS supervision | |
Recoverable gains by supervision when non-compliance | |
Punishments for local government when non-compliance | |
Extra benefits for local government when finish RPS targets |
Participation | No participation (1 − |
|
---|---|---|
Compliance (1 − |
− |
0 |
Non-compliance |
− |
− |
According to
The correlation between the above utility and regulatory probability is discussed by the derivative for
Therefore, when
The game behaviour of power grid enterprises under RPS is based on the fact that renewable sources are intermittent for electricity generation, and the grid needs to pay extra costs in the process of renewable electricity access. Therefore, the grid connection of renewable electricity is more difficult than that of traditional power [
Power system reform would have an influence on the power grid game-decision process under the quota system. The first power reform in 2002 suggested the establishment of five major tasks. The power supply chain has achieved the separation of governmental function and enterprise economic performance, the separation of power plants and power grids, and the separation of primary businesses and subsidiary businesses [
The most important task is the price adjustment and new settlement mechanism of power transmission and distribution. The electricity price includes the on-grid price (purchase price), transmission and distribution price, sales price, etc. After the electric power reform, the profit of the power grid may change from the difference between the purchase price and sale price of electricity to a price that includes operating costs and a reasonable profit. Therefore, the power grid will transition from the former profit-making unit to the public utility unit with a certain profit margin and only charge the transmission and distribution electricity price approved by the government, that is, the ‘electricity toll price’. Based on the above analysis, this section establishes a power grid decision-making model under the quota system. The model assumes that the power transmission cost function of power grid enterprises is a linear function, and the model parameters are shown in
Indicators | Parameters |
---|---|
Electricity terminal sales price | |
Electricity transmission and distribution price | |
On-grid price of conventional electricity | |
Renewable electricity subsidy price | |
Feed-in tariffs for renewable power | |
Non-renewable electricity of power producer j | |
Renewable electricity of power producer j | |
The upper limit of non-renewable electricity production of electricity producer j | |
The upper limit of renewable electricity production of electricity producer j | |
Non-renewable electricity production cost function of power producer j | |
Renewable electricity production cost function of power producer j | |
Quota proportion | |
Electricity supply from producer j | |
Power transmission cost of traditional power grid enterprises | |
Additional cost of renewable power transmission in power grid enterprises | |
Penalty function of incomplete quota system of power producer j from grid |
(1) Before the power reform, the profit price of the power grid is equal to the difference between the purchase price and sale price of electricity; that is, the difference between the grid price and the sale price is equal to
According to the assumption that the power transmission cost function of power grid enterprises is a linear function,
In
(2) Following the power reform, the profit price of the power grid is equal to the transmission and distribution cost and a reasonable profit. The government will be responsible for checking the operation cost of the power grid and determining the reasonable profit to set the transmission and distribution price
Power generation enterprises undertake the obligation of renewable electricity generation in the implementation of RPS targets [
According to the parameters in
Constraint condition | Constraints |
---|---|
Traditional power production restrictions | |
Renewable energy power restrictions | |
Total power supply | |
Target completion of quota system |
If replacing the parameters of the total power supply formula
Based on Rosen’s conclusion [
Let
In
Based on Rosen’s method [
The above equation should satisfy conditions
For the noncooperative game, that is, when each power producer maximizes its own revenue at the same time, under the given weight set
Specifically, the joint return function
If the joint revenue function is a concave function, power generation enterprises have greater control over their own revenue than do other power generation enterprises.
In scenario 1, there is only one player on the electricity supply side. All power generation enterprises are alliances for power production with good cooperation. The enterprise decision function is shown in
In scenario 2, there are two or more players on the electricity supply side. The multiplayer game of power generation enterprises is the noncooperative game of power generation enterprises for pursuing the maximization of each player’s interests. This research takes three players as an example and makes simplified assumptions on the cost function of power generation enterprises in the decision-making model, as shown in
According to the Rosen game model [
The derivation of the above equation can be given as follows:
Let
The essence of institutional change is the emergence of a high-efficiency system or the replacement of the original system by a more efficient system. According to the analysis of the above model, there are several alternative ways to improve local government participation in RPSs. The most important is to increase the incentive measures formulated by the central government, that is, increase The successful implementation of institutional change requires a sufficient number of people and nongovernmental organizations to recognize the change from the heart. To reduce the value of Institutional change brings potential profit, and the profit is greater than the cost of institutional change. The government changes the existing institutional arrangements. The results suggest that when The final step is to increase the sum of
Local governments play an important role in the implementation of the RPS. Local governments play a regulatory role with regard to other stakeholders, and they can also promote the likelihood that other stakeholders accept the RPS. In this study, there is no separate analysis of power users. Whether they accept the RPS largely depends on the promotion and publicity of the local government. When power users in a region are willing to accept renewable energy power, the local government can introduce incentives to encourage more users to accept renewable energy power, which provides a large number of potential customers for power producers and grid enterprises, ensuring that they can accurately evaluate future income and enhancing their willingness to accept RPS.
In the process of implementing RPS, the government plays the role of referee and carries out the functions of law-making and supervision. The implementation of RPS is a top-down reform that is proposed and promoted by the government. This reform can achieve its goals quickly. The government can promote the implementation of RPS by developing new technologies–those that modify the relative prices of production factors to promote the implementation of RPS and those that generate new benefits to promote the establishment of RPS. The government can harness human and material resources to develop new technologies to promote the implementation of RPS.
From the above analysis, it can be seen that, for local governments, the most important determinants of their decision regarding the intensity of quota supervision are the probability of quota compliance and the benefits they can obtain. These factors are also meaningful in improving the influence of the public on local government participation.
According to the linear function assumption between the transmission cost of power grid enterprises and power transmission, the acceptance of renewable energy power by power grid enterprises after the electric power reform is highly related to the state-specified transmission and distribution price, the comparison of the cost function between the acceptance of renewable energy and fossil fuel electricity, and the system of incentives and punishments established by the government. However, the existing performance assessment of RPS implementation at the local government level mainly focuses on the regulation of the reward and punishment system on the power generation side and seldom involves relevant reward and punishment policies for the power grid itself. This design is based on the premise that power grid enterprises can fully guarantee the consumption of renewable energy power in the implementation of provincial RPS, which is contrary to reality. Therefore, it is necessary to strengthen power grid enterprises’ responsibility for the transmission and distribution of renewable electricity.
First, among the stakeholders involved in the RPS policy regime, power generation enterprises, power grid enterprises and local governments must coordinate to achieve win-win cooperation. However, the actual operation of RPS policy requires the high engagement of power grid enterprises with great responsibility. Second, in the three links of the quota system, the most important and critical player in the connections among RPS implementation is the power grid enterprise, largely because the power grid has the largest power access responsibility and the most onerous work in collecting and issuing the power surcharge. From the power management perspective, the grid is also responsible for distributing and selling power. Most importantly, access to grid connections and the management of renewable electricity also need the support of power grid enterprises.
However, it cannot be ignored that power grid companies in China are also enterprises in a market-oriented economic system with the purposes of independent operation and self-financing. With the dual challenges of responsibility and obligation, and operation and survival, power grid companies in China have also encountered insurmountable operational difficulties. The greatest difficulty for grid companies in RPS implementation is how to utilize renewable electricity efficiently and entirely. The current situation reveals that renewable power cannot be fully connected to the power grid or cannot be sold after being connected to the grid. The fundamental reason lies in the underdeveloped economy and small power demand in the regions rich in renewable energy sources, while the nearby consumption capacity for renewable electricity in these regions is insufficient. In addition, from the viewpoint of power security, renewable energy generation has a relatively large randomness, and the power grid must be equipped with backup units or capacity markets for security issues. This situation will undoubtedly increase the additional burden or cost of the power grid. Conclusively, the existing power system is insufficient to fully consume renewable energy power, and the government should therefore accelerate power system reform.
Power market reform has a significant influence on the grid’s participation in the RPS. Before the electric power reform, the grid connection of renewable energy power had strong conditionality and the economic motivation for renewable electricity was weaker than that of traditional fossil fuel power. After the electric power reform, the conditional support of the power grid to renewable electricity increases considerably, and enthusiasm depends on the additional cost of renewable power connections and the system of incentives and punishments established by the government.
According to the results from
First, the three essential determinants for power generation enterprises to participate in the production of renewable electricity are the on-grid price of renewable electricity, the cost and benefit of traditional power production, and the enterprises’ dominance in the power generation market. Under the circumstance that the government does not impose mandatory requirements on power generation enterprises by setting the proportion of renewable energy generation, some enterprises are willing to implement renewable energy generation due to the low cost of renewable energy generation, while others are unwilling to generate renewable electricity. In this case, the core problem of the multi-player games of power generation side lies in the judgment of the penalty of each power generation enterprise by the government when the quota target is not fulfilled. Therefore, the phenomenon of free riding is not easy to occur by the penalty.
Before the reform of electric power system, the performance of renewable energy generation obligations of power generation enterprises depends on the relationship among the average income function based on the on-grid price, the average cost function of renewable energy power generation, and the loss function of non-fulfillment of renewable power generation. It involves the game behaviours among the central government (quota target setting), local government (specific punishment measures), power generation enterprises (cost function), and power grid enterprises (renewable power consumption).
After the electric power reform, the state is primarily responsible for the control of formulating the transmission and distribution price, which changes the profit model of power grid enterprises. At the same time, power generation enterprise alliances can directly sign power contracts with large power users. In this case, the power generation enterprise alliance will adopt the means of promoting technological innovation and improving the management level, reduce the average cost of renewable energy generation, and directly negotiate with power users to complete the RPS as much as possible to pursue the profit of the alliance.
The results from scenario 1 suggest that the moment will be appropriate and ripe to implement the RPS policy after the implementation of power reform measures. Electricity reform will help clarify the electricity price system and increase transparency in the implementation of the quota system.
Second, it is necessary to establish a feasible incentive and punishment system to prevent some enterprises from free riding. As the specific decision implementers, local governments should include all regional power generation enterprises within the provincial domains or power generation enterprises with a scale above into the RPS. Specific incentives and penalties include the link to newly-installed power generation from fossil fuels in the next year, the carbon emissions quota distribution for the carbon trading market, and the interaction with regional energy conservation plans. The implementation of reward and punishment measures must be guided by governmental supervision or third-party assessment.
Profit seeking is the reason why power generation enterprises participate in RPSs. Compared with the government, power generation enterprises are more market-oriented organizations. Power generation enterprises have the initiative to implement RPSs. The development of renewable energy power generation technology can reduce transaction costs in the implementation of RPSs and fully show its advantages in promoting the implementation of RPSs.
To make power generation companies willing to accept RPSs, the government should set appropriate quota targets and fully consider the costs and benefits of power producers. In the TGC market, punishing those who fail to meet the standard can encourage power producers to buy TGCs. However, punishment alone is not enough, and the transaction costs of the TGC must be reduced. The government can give subsidies, but the subsidy price should be lower than the TGC price, and trading TGCs could become the common belief of all power producers.
From the perspective of the policy system of China’s renewable energy development, the feed-in tariff policy has greatly promoted the renewable energy industry with increasing industrial competitiveness in the last 15 years. However, fiscal subsidy pressure has exceeded the sustainability of the policy regime. The renewable energy electricity surcharge has experienced an accelerated adjustment. It is fair to say that the development mechanism of the renewable energy industry is still not sound, and the development and utilization of renewable energy sources are facing difficulties in power grid access.
China’s RPS policy was implemented in 2019 and will be assessed for regional achievement. The integration of FIT and RPS policies is undoubtedly a great boon for the renewable energy industry. The fully guaranteed acquisition stipulation in the Renewable Energy Law is also expected to be realized by this policy mix. However, there is still a long way to go in this process, and it is necessary to comprehensively consider the decision-making behaviours of various interest groups in the implementation of the quota system and mobilize the willingness to participate by all parties in RPS performance.
Based on the RPS framework, this research analyses the game decisions of different interest groups regarding participating in RPS, aiming to mobilize all stakeholders to actively participate in the RPS completion process and provide policy suggestions for the development of a reasonable and effective reward and punishment system for the RPS policy regime. This research also described the synergy mechanism and economic analysis between RPSs and other renewable energy incentives, which could provide suggestions for policy adjustments to solve the dilemma of an insufficient willingness to engage in renewable energy consumption. This paper draws some conclusions from the theoretical perspective. For local governments, the target of the quota system should not be set too low or too high. It needs some effort to achieve this balance. It can set basic indicators and excellent indicators and provide incentive measures for excellent indicators. In addition, improving public support for renewable energy development can gain reputational benefits for local governments to participate in the RPS, which can help motivate local governments to participate. Compared with traditional energy power, the current power transmission mechanism is not conducive to the grid accepting renewable energy power. Power system reform aimed at combining the price formation mechanism is expected to promote the grid to absorb renewable energy and truly realize the non-discriminatory and barrier-free access to renewable energy power. The research results show that, compared with traditional energy power, renewable energy power is highly conditional on grid acceptance, and power system reform is expected to reduce the difficulty of renewable energy power grids. From the point of view of the generation side, which actually undertakes the quota generation task, it is useful to establish a system of sanctions to eliminate free riding in the process of completing the quota. Because China has implemented a fixed electricity price policy for renewable energy, the future implementation of the RPS needs to further consider its coordination and coordination with the on-grid price system.
However, this study only establishes the game decision-making conceptual model of each participant under the quota system. It would be meaningful to formulate a well-directed and practical reward and punishment system through case analysis. The game decision models established for different interest groups are isolated; designing a systematic game decision model for all stakeholders would determine the comprehensive influence of participants’ decisions under the policy. In addition, the future national carbon market will likely have synergistic effects with the RPS policy on renewable energy development through the allocation of carbon quotas for the power industry.